Attach calculation rules to a day scheme

Related topics

  1. Select the Work with day schemes menu item.
  2. On the Work with day schemes panel, select the applicable day scheme and click Calc rules.
  3. On the Work with day schemes, Attach calculation rules panel, click Add.
  4. You access the detail panel. The following fields are mandatory:
  5. Calc rule
    Enter the calculation rule to be attached to the day scheme.
    Sequence
    Enter a sequence number indicating the order in which the calculation rule should be performed for the day scheme.

    Click OK.

  6. You return to the Work with day scheme, Attach calculation rule panel. Repeat steps 3-4 to attach more calculation rules to the day scheme, if applicable. Exit the routine.