In this enquiry you can view information regarding the material line for a manufacturing order.
Function keys
| Reporting currency | View the amount(s) in system currency and reporting currency.
Note: Reporting currency is only displayed if a reporting currency has been defined in Work with companies and if the currency defined has a fixed exchange rate, i.e. the Fixed exchange rate field is set to YES in the Work with currencies file for this currency. |
| Equations | View the material equations. |
- Item
- Warehouse
- Status
- The code indicates the status of the manufacturing order.
- Variant
- Order number
- Plan start
- Plan compl
- Order quant
- Actual start
- Actual compl
- Sequence number
- Item
- The code that identifies the component item.
- Description
- The description of the component item or the entered description of a fictitious item.
- Warehouse
- The warehouse from which the component is to be issued.
- Operation number
- The reference to an operation number. This is used for backflushing of material at operation reporting and to calculate planned issue date (reservation date).
- Planned quantity
- The needed/reserved quantity in stock unit.
- Set-up quantity
- The fixed set-up quantity for materials. This set-up quantity can be deemed as an estimated reservation that you plan on consuming for the machine set-up before real production, and is independent of the order’s quantity. When manufacturing orders are entered, the components required quantity is calculated as follows: order quantity x component quantity + fixed set-up quantity.
Example:
Fixed set-up quantity = 10
Order quantity = 5
Component quantity = 1
Component required quantity = 15
- Issued quantity
- The issued quantity in stock unit.
- Planned issue date
- The date when the material is reserved.
- Pc amount
- The planned cost for the component item.
- Actual issue date
- The date when the material has been issued.
- Cc amount
- The actual cost for the component item.
- Position number
- The position number for the component item. This field can be used in the shop floor printout to print the manufacturing order bill of material in position number order.
- Drawing number
- Re-usable
- This field is only displayed if field Re-usable material is set to YES in the MFG control file. Indicates if the component is re-usable if scrapped quantity is reported. A proposal is displayed during operation reporting and the user can make a decision whether the item should be put to stock.
- Floor stock code
- The code indicates if material connected to manufacturing orders will be backflushed.