The following describes how to define the details of a rolling scheme by attaching a day scheme to it. You can attach several day schemes to one rolling scheme. They are automatically sequenced in intervals of 10.
- Select the Work with rolling schemes menu item.
- On the main panel, select the applicable rolling scheme and click Details.
- You accessWork with rolling scheme details. Click Add.
- You access the Rolling scheme details maintenance popup window. Complete the following fields:
- Sequence
- The sequence number is automatically retrieved in intervals of 10, but can be changed.
- Day scheme
- Enter the day scheme you want to be valid for the rolling scheme you are working with.
Click OK to update. You can continue to enter several day schemes. Once you are finished, click Previous twice to return to the initial panel. Exit the routine.