A completed phase has status 60 (completed). When the completed phase is re-opened, the status will be changed to 40 (started), allowing you to work with the phase.
- Select the Work with projects menu item.
- You access Work with project orders. Select the project you want to work with and click Details.
- You access Phase maintenance. Select the phase you want to open and click Open.
- On the confirmation panel click OK to confirm the opening of the project. The phase has been opened, and the status has been changed to 40 (started). Exit the routine.