Re-create workload

Related topics

The workload should be re-created if the parameters influencing the capacity (e.g., number of machines, resources per job, etc.) have been changed.

  1. Select the Work with reports/jobs – MFG orders menu item.
  2. You access Work with batch jobs. Select CALEND_CAP and click Submit job.
  3. You access Create work centre capacity. Complete the following fields:
  4. Create no of month
    Enter the number of months to be valid in the calendar capacity. The current month is the first month for which work centre capacity is created.
    Re-create workload Y/N
    Indicate if workload for open manufacturing orders should be re-created. If the capacity has been changed workload will be created based on the new capacity. Planned dates on operations and order header, however, will only be updated for those orders that have been selected according to the selection value for reschedule manufacturing orders.
    Re-create MRP workload Y/N
    Indicate if planned workload for MRP order proposals should be re-created. Only the proposals in the active version will be used for re-creation.

    See the Panel help for information about the remaining fields.

    Click OK to update the information. Exit the routine.