Report operations using milestone reporting

Related topics

Milestone reporting makes it possible to automatically create operation reporting. In a bill of routing, certain operations are defined as reporting points, meaning that reporting is done manually for these operations. The system will backflush the reporting for all other operations from the present operation to the previous reporting operation.

Note: Reporting operation on Structure maintenance, Bill of routing denotes if the operation should be manually reported. This field should be set to YES for the operations that are to function as reporting points, and to NO for the operations that are to be backflushed when the next operation is reported.

Note: Backflushing of operation is only done if quantity is reported. Calculation of actual cost will be made based upon the entered quantity in relation to the manufacturing order quantity, for those operations that are backflushed.

Operation Reporting operation Comment
10 NO Operation reporting is backflushed when operation 30 is reported.
20 NO Operation reporting is backflushed when operation 30 is reported.
30 YES Operation manually reported + operation 10 and 20 are backflushed.
  1. Select the Report manufacturing orders menu item.
  2. You access Manufacturing order reporting. Complete the following fields:
  3. Reporting date
    Defaults with today’s date. Leave as is or change to the applicable date for the reporting.
    Reporting type
    Indicate what reporting function is to be started by ticking one of the following: Operations, Other cost, Down time or Group order reporting. For this task, tick Operations.

    Click OK.

  4. You access Manufacturing operation reporting where you will report quantity for the first reporting point in the bill of routine. Complete the following fields:
  5. Order number
    Enter the manufacturing order number of the operation that is being reported.
    Operation number
    Enter the number of the operation that is defined as the reporting point for this manufacturing order.
    Approved quantity
    Enter the approved quantity for the operation.
    Stock unit
    Indicate if the quantity is entered in stock unit (set this field to YES) or structure unit (set this field to NO).
    Operation complete
    Indicate if this is the last reporting for this operation. For this task, set this field to YES.

    Click OK. Exit the routine.

    Result
    The times for operation 10 and 20 have been automatically reported and the status of all operations is 60 (completed). You can view the reported times in the Manufacturing order enquiry, Bill of routing.