On this panel you select the items for which material and/or operations should be updated from the project line. The BOM/BOR defined for the project line will replace the records in the Basic Data. Records that do not exist in the project BOM/BOR are removed from Basic Data.
If the Warehouse in BOM field is set to YES in the MFG control file, the warehouse will also be retrieved from the project line.
Text from the project is also copied to Basic Data during the update.
Options
Update BOM | Select this option to update the item’s bill of material. |
Update BOR | Select this option to update the item’s bill of routing. |
Update BOM and BOR | Select this option to update both the item’s bill of material and bill of routing. |
- Project no
- Phase
- Line
- Item
- Variant