Workload enquiry, Dep section/Work centre day/week, Op times in decimal/minutes (PRO203B)

On this panel you can view the workload for a selected work centre or department section. Planned workload refers to the active version or a selected simulation version.

Options

Workload details Select this option to view manufacturing order operations.
Planned workload Select this option to view planned workload for order proposals.

Function keys

Switch Run/machine Toggle between viewing workload times in run/labour or machine time.
Include/exclude planned wrkl Toggle between viewing times with or without planned workload. The selected mode is displayed in the top right corner of the panel.
Switch date/week Toggle between viewing capacity and workload on day or week level.
Minutes/Decimals Toggle between hours and minutes and hours and decimals for the operation times.
Net/Gross Toggle between viewing net capacity and gross capacity. The selected mode is displayed in the top right corner of the panel.
Switch department cap Only allowed for department sections. Toggle between viewing capacity for a department section from included work centres or from the calendar capacity defined in the Work centre file. The selected mode is displayed in the top right corner of the panel.

Selection fields

Work centre/Department section
The code and description that identify the selected work centre or department section.
Workload type

Click the Switch Run/machine function key to toggle between viewing workload times in run/labour or machine time.
Simulation version
The simulation version. This is only displayed if the active version is not selected. Planned workload refers to this version.
Date / week
Displays capacity and workload on day or week level. Initially this is set by the value of Workload view in the MFG control file. Click the Switch date/week function key to toggle between date and week.
Capacity
The capacity in the Calendar table. The calendar reference is stored in the Work centre table.
Workload
The workload refers to open manufacturing orders, except those with order status 00. Note: If a restriction group has been entered in the Restriction group selection field, this field will only display the workload that is related to the restriction group in question.
Pre workl
The workload refers to manufacturing orders with order status 00.
Pln workl
The workload refers to order proposals for the selected active or simulation version. The proposals are created in the Material requirements planning (MRP) batch job.
%
The workload in comparison with capacity as a percentage value. Calculated as follows; workload + preliminary workload + planned workload / capacity.
Acc diff hours
The accumulated value of all workload columns sub-contracted with the capacity.
*
This asterisk indicates that a restriction group is connected to the selected work centre for a specific date. To see the workload related to the restriction group, enter a restriction group in the Restriction group selection field and click OK.